Council Approves $4.7 Million Road Resurfacing Contract

Released August 26, 2022 03:11 PM

During their August 22 meeting, the Alpharetta City Council approved a $4,720,183 contract for milling and resurfacing approximately 21 lane miles of streets and roads in 39 locations throughout the city.  Approximately $2 million of this year’s annual road resurfacing allocation is funded by proceeds from the Transportation Local Option Sales Tax.

The chosen vendor for the work, Allied Paving Contractors will complete the work between September 2022 and June 2023.

The City of Alpharetta maintains more than 500 lane miles of streets and roads and annually budgets dollars for milling and resurfacing.  The condition of all roads in the city is periodically evaluated and that data along with historical repair, rehabilitation information, and traffic information helps the City make consistent and cost-effective decisions for roadway preservation and resurfacing.  Based on that data, the following road sections will be resurfaced under the recently approved contract:

1      Anna Lane East from Wallace Woods Lane to Cul-De-Sac

2      Anna Lane West from Wallace Woods Lane to Cul-De-Sac

3      Beacon Hill Crossing from Windward Parkway to Cul-De-Sac

4      Beacon Hill Way from Wynridge Crossing to Beacon Hill Crossing

5      Driffield Court from Eversedge Drive to Cul-De-Sac

6      Driffield Way from Eversedge Drive to Cul-De-Sac

7      Dunster Court from Eversedge Drive to Cul-De-Sac

8      Eversedge Court from Eversedge Drive to Cul-De-Sac

9      Eversedge Drive from Cul-De-Sac to Cul-De-Sac

10    Fox chase Circle from Foxthorne Way to Cul-De-Sac

11    Fox Road from New asphalt to City limits

12    Foxthorne Way from Thornbury Way to Cul-De-Sac

13    Harrington Drive from Mayfield Road to Eversedge Drive

14    Henderson Parkway from Cumming Street to HWY 9

15    Hillcrest Heights from Wynridge Crossing to Cul-De-Sac

16    Jane Wallace Lane from Wallace Woods Lane to Hammer Head

17    Marianna Lane East from Wallace Woods Lane to Hammer Head

18    Marianna Lane West from Wallace Woods Lane to Cul-De-Sac

19    Millstone Court from Henderson Parkway to Cul-De-Sac

20    Millstone Drive from Henderson Parkway to Cul-De-Sac

21    Monroe Court from Monroe Drive to Cul-De-Sac

22    Monroe Drive from Cumming Street to End

23    Monroe Way from Monroe Drive to Cul-De-Sac

24    Newcastle Drive from Eversedge Drive to Sulling Way

25    Stonebury Drive from Cul-De-Sac to Cul-De-Sac

26    Sulling Way from Cul-De-Sac to Cul-De-Sac

27    Thornbury View from Fox Road to Cul-De-Sac

28    Thornbury Way from Fox road to Stonebury Drive

29    Tiverton Court from Eversedge Drive to Cul-De-Sac

30    Wallace Woods Lane from Rucker Road to Cul-De-Sac

31    Windward Parkway from GA 400 to North Point Pkwy

32    Wynridge Crossing from Windward Parkway to Cul-De-Sac

33    Wynridge Landing from Cul-De-Sac to Cul-De-sac

34    Wynridge Path from Wynridge Crossing to Cul-De-Sac

35    Wynridge Pointe from Wynridge Crossing to Cul-De-Sac

36    Wynridge Trace from Wynridge Crossing to Wynridge Landing

37    Windward Parkway from North Point Parkway to Alderman Drive

38    Lantern Ridge Court from Cul-De-Sac to Windsor Court

39    Lantern Ridge Drive from Providence Road to Lantern Ridge Court

 

The original budget for repaving these road sections, calculated in January, was approximately $3.9 million.  Unfortunately, significant price increases for materials and labor drove final costs up by 21%, leaving City Council faced with the decision to remove 15 road sections totaling 5.72 lane miles from the list or drawing roughly $820,000 from the unallocated capital account to close the gap.

Ultimately, it was determined to be in the best interests of the community to fund the repaving of all road sections on the original list.